Question 15
VariationThe time taken to do a piece of work is inversely proportional to the number of men employed. If it takes 30 men to do a piece of work in 6 days, how many men are required to do the work in 4 days?
- A.20
- B.35
- C.45
- D.60
Show the answer and explanation
Answer: C (45)
Explanation
Men × days is constant: 30 × 6 = 180, so 180 ÷ 4 = 45 men.