Question 11
Ratio, Percentages and RatesFour boys and ten girls can cut a field in 5 hours. If the boys work at 5/4 hrs rate of which the girls work, how many boys will be needed to cut the field in 3 hours?
- A.180
- B.60
- C.25
- D.20
Show the answer and explanation
Answer: D (20)
Explanation
A boy does 5/4 of a girl's work, so 10 girls equal 8 boys and the team is 12 boys working 5 hours (60 boy-hours). To finish in 3 hours needs 60 ÷ 3 = 20 boys.