Question 30
Manufacturing AccountsStock of materials 1/1 ₦10 000
Purchase of raw materials ₦160 000
Manufacturing wages ₦420 000
Royalties ₦3 000
Stock of raw materials 31/12 ₦14 000
Calculate the prime cost
- A.N597000
- B.N579000
- C.N576000
- D.N567000
Show the answer and explanation
Answer: B (N579000)
Explanation
Prime cost = materials consumed 156 000 + manufacturing wages 420 000 + royalties 3 000 = ₦579 000.