Question 24
Manufacturing AccountsGiven:
(₦)
Direct material 2,500
Direct labour 5,000
Direct expenses 1,000
Overhead expenses 1,500
From the data above, compute the prime cost
- A.₦8,500
- B.₦7,500
- C.₦6,500
- D.₦6,000.
Show the answer and explanation
Answer: A (₦8,500)
Explanation
Prime cost = direct material + direct labour + direct expenses = 2,500 + 5,000 + 1,000 = ₦8,500.